| Location:
|
Barbados |
| Client: |
Government
of Barbados |
| Main
contractor: |
Associated
Asphalt |
| Contract
value: |
£13,200,000 |
| Contract
duration: |
2 years |
Project details:
The total resurfacing of runways and taxiways, construction of a
new concrete apron for aircraft parking and infrastructure developments
for an international commercial airport.
Maintaining
runway operations during daylight hours
Material
sourcing and testing to agreed standards
Restricted
working hours
Project
success led to additional variations being awarded at the close
of the original project
|
|

|
|
Principal activities:
Airport
rehabilitation and expansion
Runways
and taxiway resurfacing
Concrete
apron construction
Airside
equipment parking area
Car
park expansion
Road
network Improvements
International
logistics
Building
demolition
Drainage
improvements
Airfield
markings
|