| Location:
|
Benbecula, Stornoway |
| Client: |
Highlands & Islands Airport Ltd. (HIAL) |
Consultant:
|
Highlands
& Islands Airport Ltd. (HIAL) |
| Main
contractor: |
Bardon
Contracting |
| Contract
value: |
£2,200,000 |
| Contract
duration: |
8 weeks |
Principal activities:
Planing
of main runway
Resurfacing
of main runway
Entire
site occupation to reduce contract period
Use
of Marshall asphalt
ICE
5th Edition Contract - with quantities
|
|
 |
|
Project details:
As the principal contractor for HIAL, Bardon Contracting presented
a scheme to reduce the contract period, thus saving time and money
on the project. 160,000 square metres of planing and surfacing was
completed within the reduced schedule and the budget.
Minimisation
of disruption to air traffic
Nominal
effect on non airside daily procedures
Reduced
construction periods
Good
communication with client
|