Location: Manchester Airport
Client: Manchester Airport plc
Consultant:
Sir William Halcrow & Partners
Main contractor: Kennedy Asphalt
Contract value: £439,000
Contract duration: 16 weeks

Project details:

     

Principal activities:

Green Arrow Hangar development
Green Arrow Construction of 250m access road
Green Arrow 50m cast in-situ concrete retaining wall
Green Arrow Other works to an existing balancing pond
Green Arrow Extensive electrical and communication works
Green Arrow Installation of new water and gas mains
Green Arrow Programme incorporating strict H&S and security procedures

Working for Manchester Airport involves heavy programming and administration activities to ensure safe work practices and high specification finishes. These are achieved either on a runway or on a car park.

Green Arrow Adhered to stringent safety procedures
Green Arrow Adhered to stringent security procedures
Green Arrow Safety and security issues were structured into the programme in order to ensure no excess down time