| Location:
|
Manchester Airport |
| Client: |
Manchester Airport plc |
Consultant:
|
Sir
William Halcrow & Partners |
| Main
contractor: |
Kennedy
Asphalt |
| Contract
value: |
£439,000
|
| Contract
duration: |
16 weeks |
Project details:
|
|
|
|
Principal activities:
Hangar development
Construction of 250m access road
50m cast in-situ concrete retaining wall
Other works to an existing balancing pond
Extensive electrical and communication works
Installation of new water and gas mains
Programme incorporating strict H&S and security procedures
|