| Location:
|
Northampton |
| Client: |
Highways Agency |
Consultant:
|
White Young Green |
| Main
contractor: |
Associated
Asphalt |
| Contract
value: |
£9,450,000 |
| Contract
duration: |
76 weeks |
Principal activities:
5.5
km of new bypass constructed
4
new roundabouts
2
steel footbridges
Traffic
management
120,000m3
of earthworks
9,000m
of drainage
|
|
 |
|
Project details:
A successful design and build partnership project which introduced
innovative solutions, including in-situ earthwork stabilisation.
Other in-house specialist operations included surfacing, traffic
management, cold planing and the use of our UKAS lab for monitoring
quality. The route location also highlighted the company’s
ability to work with the public and local residents in an advisory
and social capacity together with managing the environmental impact
of the scheme.
Design
partner WSP Group
Route
near to residential areas
29
hectare site clearance work
80,000m²
cement-lime stabilisation
83,000m²
carriageway surfacing
|