| Location:
|
Enfield |
| Client: |
Kennet Properties |
Consultant:
|
WSP |
| Main
contractor: |
Associated
Asphalt |
| Contract
value: |
£3,000,000 |
| Contract
duration: |
40 weeks |
Principal activities:
Demolition of redundant STW comprising reinforced concrete structures,
above and below ground
Cut and fill earthworks to provide a level site for development
New roads and drainage infrastructure
Road bridge over Salmons brook
Dealt with contaminated land issues
Extensive landscaping
|
|
 |
|
Project details:
The project resulted in the provision of a fully serviced site for
commercial development.
Soil
stabilisation used which generated additional cost savings and environmental
benefits
Utilisation
of on site waste materials - concrete crushed and re-used on site
to minimise exported waste and reduce project cost
|