Civil Engineering


Cribbs Causeway Shopping Centre, Bristol

Location: Bristol
Client: Prudential Assurance Company Ltd.
Consultant:
Parkman / Ove Arup
Main contractor: Bovis Construction
Principal sub-contractor: Associated Asphalt
Contract value: £15,500,000
Contract duration: 20 weeks

Principal activities:

Green Arrow Principal sub-contractor
Green Arrow 5km of road constructed
Green Arrow Parking facilities for 7000 vehicles
Green Arrow Earthworks and rock excavations
Green Arrow Drainage facilities up to 7m in depth
Green Arrow Concrete underpass (cast in-situ)
Green Arrow Water features and landscaping
Green Arrow Decorative hard landscaping

  Cribbs Causeway Shopping Centre, Bristol  

Project details:

The project involved infrastructure works for a new shopping centre and the associated access routes and car park facilities. The co-ordination and planning of the operations were well facilitated and the project was completed and opened as scheduled.

Green Arrow Unique supply chain advantages
Green Arrow Management and operational focus on the
projects requirements
Green Arrow Committed to achieving best value for all
stakeholders
Green Arrow Maintaining public and employee safety