Civil Engineering


Manchester Piccadilly Bus Station

Location: Manchester city centre
Client: GMPTE
Consultant:
MEDC
Main contractor: Kennedy Asphalt 
Contract value: £900,000
Contract duration: 9 weeks

Principal activities:

Green Arrow Renovation and rehab of existing bus station routing and parking facilities
Green Arrow Pedestrian and traffic management scheme
Green Arrow Full road reconstruction
Green Arrow Use of different surfacing materials - hot rolled asphalt,
hardicrete wearing courses
Green Arrow Block paving
Green Arrow Footpaths
Green Arrow Traffic islands

  Manchester Piccadilly Bus Station  

Project details:

Kennedy Asphalt undertook the complex pedestrian and vehicle management schemes during construction of a redesigned multi-modal transport exchange, used by the public for bus and tram links.

Green Arrow Completed to an intense programme
Green Arrow Demonstrated ability to undertake and excel at
the most demanding urban schemes
Green Arrow Minimised disruption to public and businesses