| Location:
|
Newbury |
| Client: |
Vodafone / Highways Agency |
Consultant:
|
Buro Happold / Mott Macdonald |
| Main
contractor: |
Bovis Lend Lease |
| Principal sub-contractor: |
Associated
Asphalt |
| Contract
value: |
£5,500,000 |
| Contract
duration: |
12 months |
Principal activities:
Principal sub-contractor
On site infrastructure
Earthworks / soil stabilisation
Piling, foundations and drainage
Access roads
Car parks
Service corridors
A339 alterations and surfacing for new roundabout access
Slip roads to underpass on the A339
|
|
 |
|
Project
details:
The innovative re-design of the earthworks included a cement stabilisation
process. This innovation resulted in a reduction of over 3,000 vehicle
movements and the negation of 30,000 m3 of fill material. A more
efficient piling design allowed a significant reduction in pile
lengths on the project.
The material stabilisation and piling design
reduced both the time and cost of completion
Savings were passed on to the client
|