Yarls Wood Detention Centre, Bedfordshire

Location: Bedfordshire
Client: Home Office
Consultant:
Project Management International & Capital
Main contractor: Amey Asset Services
Principal sub-contractor: Associated Asphalt
Contract value: £10,000,000
Contract duration: 52 weeks

Principal activities:

Green Arrow Supply chain partner (Associated Asphalt)
Green Arrow Construction of new road network, parking areas, roundabouts, block paving, upgrading of 2,500m of roads
Green Arrow Construction and surfacing of sports pitches
Green Arrow All earthworks and landscaping (including internal courtyards)
Green Arrow All groundwork
Green Arrow All drainage 6,000m storm and foul drains
Green Arrow 2,500 m³ of foundation & structural concrete

  Yarls Wood Detention Centre, Bedfordshire  

Project details:

Ultimately working for the Home Office the project required adherence to strict specifications.

Green Arrow Site programming
Green Arrow Successful client communications
Green Arrow Excellent communications within the supply chain partnership
Green Arrow Secure site during and post construction of this sensitive project