| Location:
|
Bedfordshire |
| Client: |
Home Office |
Consultant:
|
Project Management International & Capital |
| Main
contractor: |
Amey Asset Services |
| Principal sub-contractor: |
Associated
Asphalt |
| Contract
value: |
£10,000,000 |
| Contract
duration: |
52 weeks |
Principal activities:
Supply chain partner (Associated Asphalt)
Construction of new road network, parking areas, roundabouts, block
paving, upgrading of 2,500m of roads
Construction and surfacing of sports pitches
All earthworks and landscaping (including internal courtyards)
All groundwork
All drainage 6,000m storm and foul drains
2,500 m³ of foundation & structural concrete
|
|
 |
|
Project details:
Ultimately working for the Home Office the project required adherence
to strict specifications.
Site programming
Successful client communications
Excellent communications within the supply chain partnership
Secure site during and post construction of this sensitive project
|