| Location:
|
Saughall Massie, Wirral |
| Client: |
Wirral MBC |
Consultant:
|
Wirral MBC |
| Main
contractor: |
Kennedy
Asphalt |
| Contract
value: |
£465,000 |
| Contract
duration: |
20 weeks
|
Principal activities:
Road and roundabout construction
Construction to Wirral MBC standards
Earthworks
5,000m2 of new road construction
Surface water drainage
Service diversions
Street lighting and fencing
Installation of new Cattle Creep
|
|
 |
|
Project details:
Another typical example of the company's ability to provide a complete
project for a metropolitan authority. Kennedy Asphalt undertook
and completed works within the scheduled time and to client specification.
The
ability to cater directly to client requirements and designs
Supply chain advantages
Local experience and insight relevant to projects
Civil construction capability
|