Local Authority


Three Lanes End, Wirral

Location: Saughall Massie, Wirral
Client: Wirral MBC
Consultant:
Wirral MBC
Main contractor: Kennedy Asphalt
Contract value: £465,000
Contract duration: 20 weeks

Principal activities:

Green Arrow Road and roundabout construction
Green Arrow Construction to Wirral MBC standards
Green Arrow Earthworks
Green Arrow 5,000m2 of new road construction
Green Arrow Surface water drainage
Green Arrow Service diversions
Green Arrow Street lighting and fencing
Green Arrow Installation of new Cattle Creep

  Three Lanes End, Wirral  

Project details:

Another typical example of the company's ability to provide a complete project for a metropolitan authority. Kennedy Asphalt undertook and completed works within the scheduled time and to client specification.

Green ArrowThe ability to cater directly to client requirements and designs
Green Arrow Supply chain advantages
Green Arrow Local experience and insight relevant to projects
Green Arrow Civil construction capability