Project details:
Replacing the waterproof layer and resurfacing one of the major
roads exiting Liverpool city centre requires excellent traffic management
and programming, especially over a rigid schedule.
Incorporating
many aspects of the Bardon Contracting business
Project
completed to time
Project
completed to budget
Resurfacing
completed within restricted area
No
disruption or damage to surrounding infrastructure or structural
integrity of the flyover
|
|
 |
|
Principal activities:
Planing
Waterproof
layer replacement
Resurfacing
with hot rolled asphalt (2,000m²)
Renewal
of the drainage system
Structural
integrity assessment of the bridge deck
Replacement
of the expansion joints
|