Contract value: £2,000,000
Contract duration: 2 years

Principal activities:

     

Project details:

During the widening traffic management was required to maintain safe use of the motorway, causing minimal delay to the travelling public.

Green ArrowSafe access and egress to the works for the workforce

Green ArrowTraffic Management works for Costain / Skanska / Mowlem Joint Venture A2 / M2 widening contract
Green ArrowAssociated Asphalt design for traffic management layout
Green ArrowMaintenance of 18 kilometres of traffic management on one of the major routes to the Kent ports
Green ArrowContract involves closures of the motorway on planned weekends with major diversion systems in operation
Green ArrowMaintenance of existing traffic flows with minimum disruption to the travelling public during peak periods
Green ArrowThe scheme fully conforms to the HA Sector Scheme for Quality Management, all operatives are fully accredited to SS12A/B